1. Home
  2. Blog
  3. Capacity Requirement Planning: Inputs, Load Checks and Strategies

Capacity Requirement Planning: Inputs, Load Checks and Strategies

  • 6 min read
  • Tranquil team

Capacity requirement planning (CRP) checks whether a factory has enough machine and labour hours to make what it plans to make, work centre by work centre and period by period. It takes the production orders that are planned or already open, multiplies the quantities by the hours each operation needs from the routing, and compares the result with the hours each work centre actually has. Where the load exceeds capacity, the planner knows before the order is late, not after.

This article explains the inputs CRP needs, how the calculation works, a worked load check for one work centre, the ways to close a gap, the broader capacity strategies, and what Tranquil ERP records for production capacity.

What capacity requirement planning does

Hands pointing at printed charts on a meeting table

Material planning answers whether the materials will be there. Capacity requirement planning answers whether the machines and people will be free to use them. A plan can have every material in stock and still fail because the paint line is booked twice over in the second week of the month.

CRP works at the level of work centres, meaning a machine, a group of similar machines or a team doing one kind of operation. Its output is a load profile for each work centre showing required hours against available hours per day or week. It is a check on a production plan, so it is only as good as the plan and the routings behind it.

Inputs needed for capacity requirement planning

  • Production orders, both planned and open, with quantities and due dates.
  • Routings for each product, listing the operations, the work centre for each and the setup and run time per unit.
  • Work centre capacity, meaning the number of machines or people, shifts, working days and planned maintenance.
  • Efficiency or utilisation, the share of available hours that turns into productive output once breaks, changeovers and minor stops are allowed for.
  • Lead times between operations, so the load falls in the right period.

The weakest input is usually the routing. Standard times set when a product was introduced are rarely updated, so comparing them with actual times from recent production is worth doing before trusting any load figure.

A worked load check for one work centre

Planner using a tablet over printed charts on a table

The figures are hypothetical. A metal workshop has three CNC cutting machines working two 8-hour shifts, 22 days in the month, at an expected efficiency of 85%. Available capacity is 3 × 16 × 22 = 1,056 hours, or 1,056 × 85% = 897.6 effective hours.

Product Run time Setups Load (hours)
A 500 units × 0.6 h = 300 3 × 4 h = 12 312
B 800 units × 0.45 h = 360 4 × 5 h = 20 380
C 300 units × 0.8 h = 240 2 × 6 h = 12 252
Total 944

The load is 944 ÷ 897.6 = about 105% of effective capacity, an overload of about 46 hours. The planner can schedule overtime, combine the two product C batches to save a setup, move part of C to the next month if its due date allows, or subcontract some cutting. The common mistake is to compare load with the full 1,056 hours, which shows spare capacity that does not exist once changeovers and stops are counted.

Ways to close a capacity gap

Overhead view of a desk with laptops, a tablet and printed charts

In the short term, capacity can be raised with overtime or an extra shift, by moving work to an alternative work centre, by subcontracting an operation, or by reducing setups through better sequencing. Load can be lowered by moving orders with flexible dates or splitting large orders.

Each option has a cost and a limit. Overtime is limited by labour rules. In Saudi Arabia the Labor Law sets normal working hours at eight a day or 48 a week, with overtime paid at a premium, so a plan that depends on overtime every week is really a sign that permanent capacity is short. Subcontracting adds cost and transport time, and moving dates affects customers.

Capacity strategies over the longer term

Four colleagues gathered around a laptop in an office

When CRP shows the same work centres overloaded month after month, the question becomes whether to add permanent capacity. Three classic strategies apply.

  • Lead, adding capacity before demand arrives, which protects service but risks idle machines if demand does not grow.
  • Lag, adding capacity only once demand has clearly exceeded it, which saves investment but risks lost orders in the meantime.
  • Match, adding capacity in smaller steps as demand grows, which sits between the two.

The choice depends on the cost of the equipment, how long it takes to install and staff, and how certain the demand is. A load history from CRP is the best evidence to bring to that decision.

Capacity planning for people and projects

Overhead view of a planner working with a laptop and charts at a desk

The same logic applies to labour in service and project companies. Instead of machine hours, the planner compares the hours each skill is booked for, such as electricians, welders or site engineers, against the hours available. A record of employee skills and certifications makes it possible to see whether the people free next week are the ones the work needs.

Production capacity in Tranquil ERP

In Tranquil’s production module, each production item has bills of materials and routings. A routing lists operations on workstation groups, and each operation carries setup time, cycle time, fixed and variable cost, and the department and workers. Workstations are recorded as assets under a workstation category. Production orders book materials, operations are started, paused and stopped with the quantity produced, and the Production Efficiency report compares estimated with actual time and cost, which helps keep routing times realistic.

For projects, a labour request is scheduled in the HR area, assigning employees to the project with their billing rates, and timesheets flow back to the project. Tranquil’s manuals do not describe an automatic capacity load profile or finite scheduling, so the load check above is prepared from routing and order data. The production planning and project management pages give more detail, and job costing in a workshop is covered in ERP for metal fabrication. To see a routing and the efficiency report on sample data, request a demo.

Frequently asked questions

What is capacity requirement planning?

A method that calculates the machine and labour hours needed by planned and open production orders, work centre by work centre and period by period, and compares them with available hours so overloads are found before orders are late.

What is the difference between CRP and MRP?

Material requirements planning works out which materials are needed and when. Capacity requirement planning takes the resulting production orders and checks whether the work centres have enough hours to process them. One plans materials, the other plans time.

How is work centre capacity calculated?

Multiply the number of machines or people by the hours per shift, the number of shifts and the working days in the period, then apply an efficiency or utilisation factor for breaks, changeovers and stops.

What can be done when a work centre is overloaded?

Add overtime or a shift within labour rules, move work to another work centre, subcontract operations, reduce setups by grouping batches, or move orders whose due dates allow it. Repeated overloads suggest permanent capacity is needed.

Tranquil in practice

In the demo we show this article’s topic on Tranquil’s own screens and answer your team’s questions.

Dammam +966 13 848 8080, +966 13 817 7724, Riyadh +966 11 213 1330
[email protected]
Sunday to Thursday, 8 am to 5 pm.